Plans for a quarry on the edge of Silsden to be reopened won't now go ahead - after a planning inspection dismissed an appeal against Bradford Council's decision to reject it.
Hundreds of people had objected to plans to re-open Horn Crag Quarry which, if approved, would have seen 520,000 tonnes of Yorkshire Stone taken from the site over a 20-year period.
Bradford Council rejected a second application from A D Calvert Architectural Stone Supplies in May 2023, saying the proposal wasn't acceptable in an “area of distinct character.” They also raised concerns about the quarry’s impact on water supplies in the area.
The applicant appealed against the decision, with an Inquiry held in February this year at City Hall in Bradford as part of the Planning Inspectorate process.
Objectors said - among other things - that the area’s roads were not suitable for HGVs, that it would damage the environment and impact local wildlife.
Planning Inspector Rachael Bust writes in her appeal decision notice:
"The permanent changes to landscape character would not be acceptable. This harm would be to a valued landscape and in my judgement the harm to the landscape weighs substantially against the proposal. Notwithstanding the phasing and restoration proposals, the temporary effects to the landscape character would also in my judgement be unacceptable for a significant period of time which weighs heavily against the proposal.
"I have carefully considered all arguments presented by the Appellant and have taken account of all other matters raised in the representations and in the oral evidence to the Inquiry in my own assessment of this scheme. Having regard to all matters, it is my overall conclusion that the aspects that weigh in favour of the proposal, specifically need, would not be sufficient to overcome the harm that I have identified and therefore the conflict with the development plan. In such circumstances, relevant material considerations do not indicate that a decision should be reached otherwise than in accordance with the development plan."
Responding to the news, Keighley and Ilkley MP Robbie Moore said:
"I'm extremely pleased to see that plans to re-open Horn Crag Quarry have been dismissed.
"Throughout this saga, I made my views clear against these plans, which would have undoubtedly had huge negative consequences for residents in the Silsden area or indeed anyone living along the access route - not to mention its effects on local wildlife and our environment.
"This is a great day for Silsden and a huge thank you must go to everyone who submitted their objections and campaigned hard for this result."

Doggy Days set to return to Ilkley Lido
Foley Films returns to Ilkley with new autumn programme
Spellman Care named Health and Wellbeing Business of the Year
Runners for Great North Run raise over £17,000 for Yorkshire Air Ambulance
Sir Gareth Southgate helps raise £23,000 for Martin House at Ilkley golf event
Ashlands Bonfire to celebrate 40th anniversary with biggest-ever fireworks display
Off-peak roadworks begin on A65 near Ilkley
Ilkley businesses become Gold Sponsor of Clarke Foley Community Hub
Ilkley takeaway named among Tripadvisor’s top 10% worldwide
McDonald's near Ilkley seeks earlier opening hours
Ilkley care home resident celebrates 106th birthday
Fresh handmade bread coming to Three Little Birds in Ilkley
Former Ilkley bistro owner teases new venture on the High Street
New Ilkley travel agency to celebrate opening with special event
Mental health campaign launched in memory of son
Yorkshire writers in spotlight at Ilkley Literature Festival
Annual golf day raises £4,383 for Airedale Hospital
The Ilkley Cow enters search for UK's Favourite Local Business
New Ilkley care home announces opening date following 11 month refurbishment
Ilkley team raises £3,300+ for The Principle Trust in Three Peaks challenge